Extended 12 Plan
This plan uses 3 teams and two 12-hr shifts to provide 24/7 coverage. Each team works 7 consecutive day shifts, 7 consecutive night shifts, then takes 7 days off
Characteristics | |
| Plan ID | C3TR12-3 |
|---|---|
| Name | Extended 12 Plan |
| Applicability | 24/7 operations |
| Teams Required | 3 |
| Shifts | Day (12-hr), Night (12-hr) |
| Repeat Cycle | 21 days |
| Rotation | Rotating between day and night shifts every week |
| Average Hours per Week | 56 |
| Staffing Fluctuation | Balanced from shift to shift and day to day |
| Pluses |
|
| Minuses |
|
| Common Usage | 24/7 operations requiring 3 teams and 12-hr shifts |
| Notes | Popular with fly-in, fly-out operations where the cost of transporting employees to a work site is high. Employees are normally flown in to work 14 straight days then flown out for 7 days. Usage examples are mining and oil rig operations. |